z. Purchase Order Award IFB 007-26 Corrugated Steel Pipe to Skyline Steel to be Used in
County Right of Ways for Maintaining the Storm Water Infrastructure in the Amount of
$50,000.00.
Daniel Roberts, Assistant Director, Operations — Public Works Operations
Attachments:
aa. Purchase Order for Materials Only through Valmont Industries from Build26 to Acquire
Traffic Signal Poles for the Highlands Ranch Parkway (Broadway to Burntwood)
Reconstruction Project, Douglas County Project Number CI 2026-005 in the Amount of
$258,698.82. In Addition, Further Approval to Either Order Additional Project Materials, or,
if the Traffic Signal Poles Pricing Should Change, for an Additional Amount Not to Exceed
$91,301.18. The Total of all Project Materials is $350,000.00.
Amy Strouthopoulos, P.E., Pavement Management Supervisor — Department of Public
Works Engineering
Attachments:
ab. Intergovernmental Agreement Between the Town of Larkspur and the Board of County
Commissioners of the County of Douglas, State of Colorado, Concerning the Town of
Larkspur Asphalt Resurfacing Project, and Associated Change Order #1 with Martin
Marietta Materials, Inc., to the 2026 Asphalt Overlay Project Contract, in the Estimated
Amount of $431,337.26, Douglas County Project Number CI 2026-003.
Amy Strouthopoulos, P.E., Pavement Management Supervisor
Attachments:
ac. Amendment Number Four for Public Contract for Services for 2025-2026 Conveyance
Regulation Services to Shums Coda Associates, LLC in the Amount of $120,080.00.
Matthew Dziubanski, Chief Building Official — Department of Public Works Engineering
Attachments: