ac. Circular Edge JDE 2025-2026 Functional and Developmental Support in the Amount of
$240,000.00.
Mike Wise, Deputy Director of IT for Application Services — Information Technology
Attachments:
ad. Construction Contract Change Order 3A with Kraemer North America, LLC for an Amount
not to Exceed $1,200,000.00 for the US Highway 85 (Highlands Ranch Parkway to Dad
Clark Gulch) Widening Project, CDOT Project Number STU 0852-118 (23474) and Douglas
County Project Number CI 2022-021.
Arthur E. Griffith, Transportation CIP Manager — Department of Public Works Engineering
Attachments:
ae. Public Contract for Services, for an Amount not to Exceed $96,804.70 to Rocksol Consulting
Group, Inc. for the Dakan Road Bridge Replacement Project, Douglas County Project
Number CI 2007-021.
Neil Sarno, Project Engineer — Department of Public Works Engineering
Attachments:
af. Public Contract for Services (PCS) with Alfred Benesch & Company, Inc. (Benesch) for the
Waterton Road / Eagle River Street Roundabout Project, in the Amount of $219,455.00,
Douglas County Project Number CI 2025 - 007.
Sean P. Owens, PE, Special Projects Manager — Department of Public Works Engineering
Attachments:
ag. Construction Contract with Villalobos Concrete, LLC for the Waterton / Eagle River
Roundabout Project, in the Amount of $2,991,496.22, Douglas County Project # CI 2025 -
007.
Sean P. Owens, P.E., Special Projects Manager — Department of Public Works Engineering
Attachments: