t. Dust Suppressant and Soil Stabilization IFB012-26 for Award Orders in the Amount of
$200,000.00 to Dustpods, LLC, $125,000.00 to Team Laboratories Chemicals, LLC and
$150,000.00 to Envirotech Services.
Daniel Roberts, Assistant Director, Operations — Board of County Commissioners Business
Meeting and Potter
Attachments:
u. Amendment 1 to Public Contract for Services with B2P, Inc. dba Basis Partners for the
Additional Amount of $425,000.00, for the Hilltop Road Project - Segment 1; Douglas
County Project Number CI 2020-029.
Cori Cowan, P.E., Capital Improvements Project Engineer — Department of Public Works
Engineering
Attachments:
v. Amendment 1 to Public Contract for Services with HDR Engineering, Inc. for Design
Services During Construction on the Hilltop Road Improvement Project, for an Additional
$24,837.00, Which Takes the Original Contract Amount over $100,000.00, Requiring Board
of County Commissioners Approval; and will Also Extend the Expiration Date of the
Contract Through June 30, 2027; Douglas County Project Number CI 2020-029.
Benjamin Pierce, P.E., Capital Improvements Projects Supervisor — Department of Public
Works Engineering
Attachments:
w. Construction Contract with Mocon Pacific, Inc. for the 2026 Urban Storm Sewer UV CIPP
Lining Project in the Amount of $191,000.00; Douglas County Project # SP 2026-012.
Deborah E. Kula, P.E., Special Projects Engineer — Department of Public Works
Engineering
Attachments: